OPTIMALISASI SUMBER DAYA MANUSIA DENGAN PENERAPAN METODE PRECEDENCE DIAGRAM METHOD PADA PROYEK REKONSTRUKSI JALAN

  • Muhammad Syarif Hidayatullah
  • Ratri Andinisari ITN Malang

Abstract

This study analyzes time acceleration and cost impacts on the Rajekwesi Kalipare–Donomulyo road reconstruction project using the Precedence Diagram Method (PDM) and human resource optimization based on workload balancing and worker productivity. Employing a quantitative descriptive methodology with BoQ and technical drawings data, analysis via Microsoft Project and Excel evaluated three acceleration alternatives: (1) added equipment/workers, (2) extended work hours, and (3) simultaneous execution of similar tasks at three points. Results show the original 66-day duration can be reduced to 53 days (Alt 1), 62 days (Alt 2), and 65 days (Alt 3), but with cost increases from Rp2,437,614,513.92 to Rp2,604,160,281.51 (+6.83%), Rp2,536,240,546.97 (+4.05%), and Rp2,714,391,506.94 (+11.35%) respectively. The acceleration reduces duration yet raises costs, necessitating balanced consideration of time efficiency and budget constraints when selecting alternatives.

Downloads

Download data is not yet available.
Published
2026-10-30