ANALISIS PERCEPATAN JADWAL PROYEK KONSTRUKSI MENGGUNAKAN METODE CRASHING PADA PROYEK RUMAH SAKIT HERMINA KEPANJEN
Abstract
The New Building Construction Project of Hermina Kepanjen Hospital in Malang Regency, with a total building area of 1,596 m2 (6 floors), experienced a delay in physical progress from week 6 to week 10. By the end of week 10, the cumulative progress deviation reached -12.773%, requiring an effective schedule recovery strategy. This study aims to analyze the implementation of the crashing method by adding 3 hours of overtime daily (70% efficiency) on critical structural activities after week 10. The critical path was identified using the Critical Path Method (CPM). The analysis reveals that among 16 activities, 7 critical structural activities were targeted for crashing. The implementation reduced the normal duration of critical activities from 63 days to 51 days, achieving a time reduction of 12 days (19.05%). The direct cost increased by IDR 3,674.19 million or 23.98% over the total normal cost (from IDR 15,320.59 million to IDR 18,994.78 million). Based on the cost slope ranking, Column and Shear Wall 4th Floor had the lowest cost slope at IDR 174.17 million/day, making it the highest priority for compression.