PENERAPAN METODE PREDENCE DIAGRAM METHOD UNTUK PENJADWALAN DAN PEMBIAYAAN PROYEK PEMBANGUNAN RUMAH SAKIT
Abstrak
This study aims to analyze cost and time planning in the construction project of a hospital in Bululawang, Malang Regency. The technical data used includes working drawings, volume calculations, Unit Price Analysis (AHSP), and the Budget Plan (RAB). The project was analyzed using the Work Breakdown Structure (WBS) method to break down project phases, and the Precedence Diagram Method (PDM) for scheduling. The analysis shows that the project’s duration in the existing plan is 328 days with a total cost of IDR 3.239.140.000. To accelerate the project timeline, additional labor was employed, reducing the duration to 269 days. However, this acceleration resulted in an increased project cost of IDR 4.121.620.000. The comparison between the existing and accelerated schedule and budget reveals a trade-off between time and cost, which must be carefully considered in construction project management.