PENERAPAN METODE PRECEDENCE DIAGRAM METHOD DALAM PENJADWALAN PROYEK JALAN SIMPANG BATU-LABURAN KABUPATEN PASER, KALINMANTAN TIMUR
Abstrak
Construction project scheduling plays a vital role in ensuring time efficiency and coordination among project activities. This study aims to develop a project schedule for the road improvement project at Simpang Batu–Laburan, located in Paser Belengkong District, East Kalimantan Province, using the Precedence Diagram Method (PDM). The data utilized include design drawings and the Bill of Quantities (BoQ), analyzed with the aid of Microsoft Project Professional. The results indicate that the total project duration using the PDM method is 114 calendar days, with several activities identified on the critical path, meaning they have zero float. One of the non-critical activities, namely the subbase concrete layer work, has the highest total float of 63.5 days. The application of PDM proved effective in providing a systematic scheduling structure, accurately identifying the critical path, and supporting efficient project time management.